References

Selection of the buildings we participated

References list

Over the past years we have successfully completed the following construction projects:

Project Dates Description
Forum der Zahnradfabrik Friedrichshafen September 2015 – May 2016
  • 6500 m2 6500m2 plasterboard ceiling with integrated cooling System
  • 3500m2 inactive perforated plasterboard roof
  • 2000m2 plasterboard walls
  • 1000m2 facing shells
Illertal – Gymnasium in Voehringen November 2015 – May 2016
  • 1800m2 plasterboard ceiling with integrated cooling System
das Aerztehaus Heidenheim March 2016 – August 2016
  • 2000m2 coffered cooling Roof
Bau 120 Freudenberg, Verwaltungsgebäude, Weinheim April 2016 – March 2017
  • 3000m2 plasterboard cooling sails
  • 4500m2 plasterboard ceiling with integrated cooling System
  • 255m2 high performance blade roof cooling System
Lech Stahlveredelungswerk, Oberndorf a. Lech June 2016 – July 2016
  • 550m2 perforated plasterboard ceiling with integrated cooling System
MPI, Max-Planck-Institut i. Heidelberg August 2016 – September 2016
  • 450m2 perforated plasterboard ceiling with integrated cooling System
Knauber Bonn November 2016 – January 2017
  • 1200 m2 perforated plasterboard ceiling with integrated cooling System
Weishaupt Neuss Buro November 2016 – December 2016
  • 650 m2 perphorated radiant plaster ceiling
ZF Saarbruecken Buro November 2016 – March 2017
  • 1800 m2 – radiant modular grid ceiling
DKFZ Heidelberg, Radiologisches Krebsforschungszentrum Heidelberg December 2016 – March 2017
  • w. 450 pieces of metal roof sails
Koln WDR studio 1 December 2016 – January 2017
  • 350 m2 perphorated radiant plaster ceiling
Dusseldorf Seestern Buro January 2017 – September 2017
  • 18 800 m2 radiant modular grid ceiling
Hotel Moxy Frankfurt am Main January 2017 – April 2017
  • 5200 m2 plaster walls
Schnelldorf Groningen GmbH Buro February 2017 – April 2017
  • 400 m2 perphorated radiant plaster ceiling
Cewe Oldenburg Buro March 2017 – June 2017
  • 1600 m2 perphorated radiant plaster ceiling
Amadeus Fire Frankfurt Am Main Buro April 2017 – September 2017
  • 350 m2 – perphorated radiant plaster ceiling
  • 450 pcs – radiant ceiling panels
  • 700 m2 – modular grid ceiling
Dailmer AG Stuttgart Buro June 2017 – still work on it
  • 5200 m2 radiant coffered ceiling
Heilbronn Triple Buro June 2017 – October 2017
  • 1600 m2 perphorated radiant plaster ceiling
Polizeipraesidium Mönchengladbach June 2017 – November 2017
  • 880 pcs alluminium radiant plates
  • 180 m2 radiant coffered ceiling
TeNnet Bayreuth Buro June 2017 – November 2017
  • 550 pcs metal radiant plates
  • 1200 m2 perphorated radiant plaster ceiling
Essen Noweda Buro July 2017 – October 2017
  • 2000 m2 perphorated radiant plaster ceiling
Fiat Universum August 2017 – September 2017
  • 2250 m2 mineral fibre ceiling
MAN Munchen Buro August 2017 – October 2017
  • 1200 pcs metal radiant hanged plates
Stettler Kunststofftechnik Beteiligungs GmbH Burgwindheim August 2017 – October 2017
  • 680 m2 radiant coffered ceiling
Wallau Ikea Buro August 2017 – October 2017
  • 1340 m2 alluminium radiant plates
Q-DAS Business Campus Buro August 2017 – October 2017
  • 1150 m2 metal radiant plates
  • 100m2 perphorated radiant plaster ceiling
Insbruck Flughafen Buro September 2017 – November 2017
  • 1300 m2 Radiated Alluminium hanged ceiling
Boarding House Kapstadtring Hamburg Hotel October 2017 – January 2018
  • 4200 m2 perphorated radiant plaster ceiling
  • 400 m2 Carbon radiant ceiling system
Essen Freiheit Buro January 2018 – February 2018
  • 400 pcs metal cooling sails
Wabco Hannover Buro January 2018 – April 2018
Feuerwache Hannover Buro March 2018 – April 2018
  • 200 m2 radiant coffered ceiling
Giebelstadt Schulle March 2018 – May 2018
  • 300 m2 – perforated plasterboard ceiling with integrated cooling System
  • 52 pcs radiant ceiling panels
Munchen Bank Buro March 2018 – July 2018
  • 7600 m2 grid ceiling
Berlin Zalando Buro April 2018 – October 2018
  • 7780 m2 metal radiant plates
  • 400 m2 perphorated radiant plaster ceiling
Frankfurt am Main Buro April 2018 – August 2018
  • 2500 m2 radiant modular grid ceiling
Hotel Bad Kreuznach April 2018 – June 2018
  • 1000 m2 plasterboard ceiling with integrated cooling System
Paragon Buro April 2018
  • 200 m2 radiant coffered ceiling
St. Augustin BMW April 2018
  • 400 m2 perphorated radiant plaster ceiling
Feuerwache Kaarst May 2018
  • 300 m2 plasterboard cooling sails
Berlin Buro August 2018 – November 2018
  • 1000 m2 coffered cooling Roof
  • 70 pcs radiant ceiling panels
BP Lingen August 2018 – December 2018
Feuerwache Erlangen August 2018
  • 60 pcs radiant ceiling panels
TUV SUD Munchen Buro August 2018 – November 2018
  • 1000 m2 perforated plaster
Alter Wall Hamburg Buro September 2018 – 2019
  • 7100 m2 perphorated radiant plaster ceiling
Bad Kreuznach Bank Sparkasse September 2018 – February 2018
  • 1500 m2 plasterboard cooling sails
  • 1500 m2 plasterboard ceiling with integrated cooling System
Buro Berlin September 2018
  • 70 pcs radiant ceiling panels
Buro Gemmrigheim September 2018
  • 100 pcs radiant ceiling panels
Flughafen Koln/Bonn DHL Buro September 2018 – January 2019
  • 1400 m2 radiant modular grid ceiling
Leitwarte Herne September 2018
  • 100 m2 perphorated radiant plaster ceilingli
Stadtwerke neustadt holstein September 2018
  • 60 pcs radiant ceiling panels
Buro Zell am He October 2018
Jena Schule October 2018 – 2019
  • 5100 m2 suspension system
Buro Bonndorf Schwarzwald November 2018
  • 220 m2 radiant modular grid ceiling
VKZ Warnemunde Rostock Buro November 2018
  • 200 m2 clamping system – cooling
Bremen City Gate Buro February 2019 – 2019
  • 3700 m2 perphorated radiant plaster ceiling